Project timeline
| Civil - on site access tracks | Sept 2011 | |
| Civil - turbine foundations | Late 2011 | |
| Turbine delivery and erection | March - April 2012 | |
| Testing phase | June - July 2012 | |
| Operational | End July 2012 |
Community consultation
Community exhibition
Community exhibition
Wind farm trip I
Wind farm trip II
Met mast application
Met mast constructed
Scoping request
Planning submission
Appeal lodged
Appeal decision
Operational
Planning approved
Community consultation
Year 1
Site investigation
Site investigation
Year 2 - 5
Development process
Development process
Year 6
Construction
Construction